Work halted on Panama Canal expansion

By Tom Stieghorst

The Panama Canal Authority said almost all activity has ceased on the project to widen the canal, amid a payments dispute with the contractor.

A consortium led by Spain’s Sacyr Vallehermoso is seeking reimbursement for cost overruns of more than $1 billion.

Two weeks of negotiations have not produced a resolution, the authority said.

Canal Administrator Jorge Quijano said the authority continues to try to find a solution, but stressed that the contractor must resume normal activity, which is critical during the dry season in Panama.

The widening project had been scheduled for completion in mid-2015. Current canal passage is not affected.

Authority assures that Panama Canal widening will be completed

By Tom Stieghorst

The Panama Canal Authority has reaffirmed its intent to finish its expansion project by mid-2015, despite a payment dispute with contractors.

A consortium led by Spanish construction company Sacyr threatened last week to suspend work on Jan. 20 if the Panama Canal Authority did not pay for $1.6 billion in cost overruns.

In a statement, the authority said its contract includes guarantees that will allow the completion of the new locks, even if it needs to step in to assume control of the project.

The authority stressed that the dispute relates only to the expansion and is not affecting current operations.

The $5.25 billion widening project will allow for longer, deeper ships to pass through the canal, which was built in 1914. The project is 72% done, the authority said.

According to Agence France-Presse, the Spanish government has begun mediating the dispute, and the Spanish minister of public works flew to Panama on Monday to talk to both sides.

Grupo Unidos por el Canal blames the cost overrun on faulty geological studies done by the authority.

In its statement, the authority said the arguments raised by Grupo “lack legal basis, are not clear and do not give any reasons for the contractor to suspend the work.”